Content Image

Content Image

Content Image

Name of Project: Khalifa Port Interchange (Truck Road Bridges)

Contract No.: DOT/C/HW/155/09
Client: Department of Transport (DOT), Abu Dhabi, UAE
Consultant: Mouchel Aurecon
Main Contractor: Larsen & Toubro Limited

Description of The Project

The Project Comprise the construction of two bridges at the Intersection of Truck Road and the New (Abu Dhabi – Dubai) Road. The bridges are post-tensioned voided slab with a width of 29.6m and a length of 60m for each bridge. The bridges are supported by means of piers and pile cap resting over a deep pile of (1.2m) diameter and 20 depths.

Scope of works:

The scope of the work comprises concrete, formwork, reinforcement and ancillary work
required for the construction of Bridges